Most of India’s tile exports come out of one place: the ceramic cluster around Morbi in Gujarat, a few hours by road from the ports of Mundra and Kandla. For a first-time importer that concentration is good news. Capacity is enormous, designs change quickly and the export routine is well rehearsed. The flip side is that hundreds of factories and traders compete for your attention, and the quality of a first container depends far more on how the order is specified than on which catalogue you liked.
This guide walks through the sequence we follow with every new buyer, from the first enquiry to the day the container is emptied in your warehouse.
Key takeaways
- Specify size, thickness, finish, grade and destination port before asking for prices — vague requests get vague quotes.
- Approve physical samples and agree shade, calibre and packing in writing on the proforma invoice.
- Standard terms are 30% advance and 70% against a copy of the bill of lading, or an LC at sight.
- Check your own market’s duty, certification and labelling rules before production starts, not after loading.
- Plan on roughly 6–10 weeks from order to delivery for long-haul markets; nearby Gulf and South Asian ports are faster.
1. Write a specification, not just a wish list
A useful first enquiry answers five questions: which sizes and thicknesses, which finishes (glossy, matt, satin, structured), which product type (glazed vitrified, polished glazed, double charge, full body, ceramic wall, 20 mm outdoor), roughly how many square metres, and which port the goods should arrive at. If you already know your target price band and Incoterm, say so.
With that information a serious exporter can reply with something you can act on: a price per square metre on a stated basis (usually FOB Mundra), pieces and square metres per box, box weight, how many boxes fit in a 20ft container, the lead time and the payment terms. If the reply is only a PDF catalogue and a request to “tell us your requirement”, you have learned something about the supplier.
2. Ask for samples — and look at more than the face
Photographs flatter tiles. Ask for physical samples of every design you are seriously considering. Most Indian exporters send trade samples free and ask the buyer to pay the courier, often crediting that cost against the first order. When they arrive, check:
- Edges and flatness — lay two pieces side by side on a flat surface. Rectified tiles should meet cleanly.
- Back stamp and thickness — measure it; 9 mm and 8 mm look the same in a photo.
- Surface — for polished tiles, check for pinholes and polishing marks under a raking light.
- Design repetition — ask how many different faces the design has. A large floor laid with only a few faces can look repetitive.
3. Get a proforma invoice that says everything
The proforma invoice (PI) is the contract most first orders run on. Before paying anything, make sure it states the product code and size, grade, thickness, finish, quantity in boxes and square metres, unit price and currency, Incoterm and named port, payment terms, expected loading date, packing specification and the shade and calibre rule (one shade and one calibre per design per lot is normal). It should also state how breakage and quality claims are handled. A good PI prevents most disputes.
Price basis
Indian exporters usually quote FOB Mundra: the price covers the goods, export packing, inland haulage, customs clearance in India and loading on board. Freight and insurance to your port are then either arranged by your own forwarder or quoted separately as CFR or CIF. Read our guide on reading FOB and CIF quotations before comparing offers.
4. Agree payment terms you are comfortable with
The common structure for first orders is 30% advance by bank transfer when the PI is confirmed, and the remaining 70% against a scanned copy of the bill of lading once the container has sailed. The exporter releases the original bill of lading (or a telex release) after the balance arrives. An irrevocable letter of credit payable at sight is the other mainstream option and is often preferred for larger orders or where your bank requires it. Be cautious of anyone asking for 100% in advance on a large first order, and do not expect open-account credit until a relationship exists.
5. Check your own market’s rules before production
This is where first containers go wrong. Duties, anti-dumping measures and product certification are set by the destination country, and some are specific to the factory that made the goods. A few examples, all indicative and subject to change:
- Saudi Arabia requires the producing factory to hold the Saudi Quality Mark and each shipment to carry a SABER certificate.
- Kenya requires a KEBS PVoC certificate of conformity issued before shipment.
- The UK expects a UKCA or CE Declaration of Performance to EN 14411, and India-origin tiles can enter at 0% duty under the India–UK CETA with a valid origin claim.
- GCC countries apply anti-dumping duties on tiles that vary by producer, so the factory named on the certificate of origin matters.
Ask your customs broker to confirm the tariff code and duty before you order, and ask the exporter which certificates are available for the exact product and plant. Our export market pages summarise the main points for ten destinations.
6. Production, quality control and loading
Stock designs can often load within two weeks of the advance; made-to-order designs commonly take three to four weeks ex-factory. During this time a good exporter confirms the shade and calibre codes for your lot and carries out a pre-shipment inspection: measuring size and flatness, checking the surface, and counting boxes and pallets.
You are entitled to send your own inspector. Independent agencies such as SGS, Bureau Veritas, Intertek or QIMA can inspect at the factory before loading; it costs a modest fee per visit and is worth it for a first order. Ask for photographs and a short video of the container being loaded, showing the container number and the seal.
Packing that survives the voyage
Specify export-grade cartons, corner protectors, interleaving on polished faces, strapping and stretch wrap, on ISPM-15 heat-treated pallets. Pallets should be loaded tightly with airbags or dunnage in any gaps. In-transit breakage of up to 1–2% is generally treated as normal; well-packed containers usually do better.
7. Shipping documents
After sailing you should receive scans of the commercial invoice, packing list, bill of lading, certificate of origin and, for CIF shipments, the insurance certificate, plus any certificates your market requires. Check that names, quantities, weights and container numbers match across every document — a mismatch can hold a container at the destination port. If your country has a trade agreement with India, ask for a preferential certificate of origin or origin statement so your broker can claim the lower duty.
8. Clearance, delivery and the first inspection
Your broker files the import declaration, pays duty and VAT or GST, and arranges delivery. When the container is opened, photograph the intact seal and any damaged pallets before unloading further, and note damage on the delivery receipt. Report problems to the exporter promptly with photos and pallet labels; most exporters handle excess breakage as a credit or replacement on the next order, and on CIF shipments the insurer may also be involved.
How long does it all take?
As a rough guide: a week or two for specification and samples, three to five weeks for production and loading, then the sailing. From Mundra that is a few days to Oman or Sri Lanka, around ten days to Singapore or Mombasa, roughly a month to the UK and five to six weeks to the US East Coast — with 2026 Gulf routing currently slower than normal. Add a few days for clearance at each end. Book your first order with a margin of time and the second one will be easier.
If you would like us to price a first container or send samples, use the sample request form or our export terms & FAQ page.